These kinds of structures GP "Hidrotehnika-Hidroenergetika"
was executing mainly within scope of large hydro-technical projects
Road Redjma - Gattara, Libya | |
Length | 9.5 km |
Width | 8m |
Construction time | 1970-1971 "Wadi Gattara" Dam Project |
Road Derna-Bu Mansur, Libya | |
Length | 24 km |
Width | 8 km |
Construction time | 1975-1977 "Wadi Dernah" Dam Project, including construction of 10 bridges with total length of 350 m. |
Railway Beograd-Bar, Yugoslavia | |
Total length | 12,8 km |
Construction time | 1969-1973 |
Railway Gardimaou - Tunis | |
Constructed within Sidi Salem dam project in period between 1978-1981. Railway is 28 km long with three bridges of metal construction and total length of 360 m. 40 various hydro-technical structures were constructed as well. | |
Excavation | 1.560.000 m3 |
Embankment | 970.000 m3 |
Railway Mateur-Beja, Tunis | |
| 15 km |
Construction time | 1981-1984 |
Excavation | 1.835.000 m3 |
Embankment | 850.000 m3 |
Concrete | 8.000 m3 |
Bridges on railways and roads | |
Length total | 3.300 m |
Height max. | 80 m |
Construction time | 1950-1990 |
Uskočka 8, Belgrade, phone: 011/2181-888, fax:011/2620-548